Management Organizations

for Tung Chung New Town Extension (West)

(EP No. EP-519/2016)

 

 

 

 

 

December 2025

 

A close-up of a document

AI-generated content may be incorrect.

 


 

1.                  Introduction

The Environmental Impact Assessment (EIA) Report (Register No.: AEIAR-196/2016) prepared for the "Tung Chung New Town Extension" (hereinafter referred to as "the Project") has been approved by the Director of Environmental Protection, and an Environmental Permit (EP) (Permit No.: EP-519/2016) has been issued for the project under the Environmental Impact Assessment Ordinance.

The submission of Management Organizations has been prepared in accordance with Condition 2.11 of the EP, which includes the following information:

(a)               the management organization of the main construction companies and/or any form of joint ventures associated with the construction of the Project;

(b)              the management organization of the Environmental Team (ET); and

(c)               the management organization of the independent Environmental Checker (IEC) and the supporting team.

The development of Tung Chung New Town Extension (TCNTE), comprising Tung Chung East (TCE) and Tung Chung West (TCW), is a mega-scale and complex project aiming to provide land to meet the future housing economic and social development needs of Hong Kong. Due to the fact that the proposed works are geographically separated, the implementation of mega-scale Project is divided into two packages, namely TCE and TCW respectively. In accordance with the tight delivery programme, the Project will be implemented in phases under separate contracts for the developments of TCE and TCW. This submission only covers the management organizations for TCW.  Management Organizations for TCE can be found at dedicated project website: http://env.tcnte.hk/ep-submissions.html.

 

2.                  Management Organization of the Main Construction Companies

2.1              Contract No. NL/2020/05 – Tung Chung New Town Extension – Site Formation and Infrastructure Works at Ma Wan Chung

Build King – Richwell Civil Joint Venture (BKRCJV) is the contractor appointed to undertake the site formation and infrastructure works at Ma Wan Chung. Names of the responsible persons and their contact details are set out in Table 1 below.

Table 1: Contact Information of the Main Construction Companies

Name

Position

Telephone

Email

Eric Yip 

Project Manager 

9196 6098 

ericyip@buildking.hk 

Artie Wong 

Construction Manager 

9633 0977 

artiewong@richwellcivil.com 

Ricky Hon 

Site Agent 

9100 7509 

rickyhon@richwellcivil.com 

Andy Kwan 

HSE Manager 

9400 9422

andykwan@richwellcivil.com

Calvin Chan 

Environmental Officer 

6117 2894 

calvinchan@richwellcivil.com 

The organization chart of the main construction companies required under EP Condition 2.11 is given in Attachment I.

2.2              Contract No. NL/2020/06 – Tung Chung New Town Extension – Site Formation and Infrastructure Works at Tung Chung Valley, Phase 1

China Railway Group Limited (CREC) is the contractor appointed to undertake the site formation and infrastructure works at Tung Chung Valley, Phase 1. Names of the responsible persons and their contact details are set out in Table 2 below.

Table 2: Contact Information of the Main Construction Companies

Name

Position

Telephone

Email

Andy Yeung

Project Director

6266 0716

andy.yeung@crec.com.hk

Jeffrey Woo

Project Manager

5538 0950

jeffrey.woo@crec.com.hk

Samuel Sim

Site Agent

6105 8233

samuel.sim@nl202006.com

Chris Lai

Construction Manager

9060 4362

chris.lai@nl202006.com

Simon Mak

Environmental Officer

6266 0745

simon.mak@nl202006.com

Hua Xinrong

Superintendent

6582 3049

xinrong.hua@nl202006.com

Chong Yau Fai

General Foreman

6266 0708

jon.chong@nl202006.com

Lee Kam Tai

General Foreman

5373 2435

NA

Chan Man

General Foreman

6266 0765

NA

The organization chart of the main construction companies required under EP Condition 2.11 is given in Attachment II.


 

2.3              Contract No. NL/2023/10 – Tung Chung New Town Extension – Infrastructure Works at Tung Chung Valley, Yu Tung Road and Ma Wan Chung

CREC Joint Venture (CRECJV) is the contractor appointed to undertake the infrastructure works at Tung Chung Valley, Yu Tung Road and Ma Wan Chung. Names of the responsible persons and their contact details are set out in Table 3 below.

Table 3: Contact Information of the Main Construction Companies

Name

Position

Telephone

Email

Steven Song

Project Manager

9085 9172

steven.song@crecjv-tc.com

Esmund Ng

Construction Manager

9520 5809

esmond.ng@crecjv-tc.com

Chi Pan Ting

Environmental Officer

4403 8391

pan.ting@crecjv-tc.com

Da Shu Jiang

Senior Site Engineer

9389 5286

dashu.jiang@crecjv-tc.com

Jason Lo

Senior Site Engineer

9793 2193

jason.lo@crecjv-tc.com

Kwok Fung Li

Site Engineer

9242 1448

johnathan.li@crecjv-tc.com

The organization chart of the main construction companies required under EP Condition 2.11 is given in Attachment III.


 

2.4              The Entrustment Agreement No. ENT/TUE/001 – Construction of Infrastructure Works in the Tung Chung New Town Extension Area

Bouygues Dragages (1201) Joint Venture (BDJV) is the contractor appointed to undertake the site formation and infrastructure works at Area 33. Names of the responsible persons and their contact details are set out in Table 4 below.

Table 4: Contact Information of the Main Construction Companies

Name

Position

Telephone

Email

Clement Chasset

Project Director

9707 8166

clement.chasset@dragageshk.com

Remi Ribet

Construction Manager

9707 8326

re.ribet@dragageshk.com

Gena Tsang

Environmental Officer

6276 4423

gena.tsang@dragageshk.com

Jonathan Leung

Site Agent

6017 6276

jonathan.leung@dragageshk.com

Ludovic Truffy

Construction Supervisor

9707 2747

lu.truffy@dragageshk.com

Ken Kwok

Environmental Supervisor

9705 6110

kenkw.kwok@dragageshk.com

Derek Ng

Environmental Supervisor

9705 6352

derek.ng@dragageshk.com

Berlin Lee

Environmental Supervisor

9707 7130

paklam.lee@dragageshk.com

The organization chart of the main construction companies required under EP Condition 2.11 is given in Attachment IV.

 

 


 

3.                  Management Organization of the Environmental Team

The management organization of the Environmental Team (ET) for TCW, including names of the ET Leader and Deputy ET Leaders and their contact details are set out in Table 5 below:

Table 5: Contact Information of the ET

Name

Position

Telephone

Email

Daniel Sum

ET Leader

2585 8495

daniel.sum@mottmac.com

Heidi Yu

Deputy ET Leader

2828 5704

heidi.yu@mottmac.com

 

The organization chart of the ET required under EP Condition 2.11 is given in Attachment V.

 


 

4.                  Management Organization of the Independent Environmental Checker and the Supporting Team

The management organization of the Independent Environmental Checker (IEC), including names of the IEC and Deputy IEC and their contact details are set out in Table 6 below:

Table 6: Contact Information of the IEC

Name

Position

Telephone

Email

Manuel Chua

IEC

3894 9501 / 2608 7314 

chuawo@binnies.com

Edward Lau

Deputy IEC

3894 9502 / 6848 5737 

lauky@binnies.com

 

The organization chart of the IEC and the supporting team required under EP Condition 2.11 is given in Attachment VI.

 

 

 

 

 

 

Attachment I

 

Organization Chart of Contract No. NL/2020/05

Build King – Richwell Civil Joint Venture (BKRCJV)


 

 

A diagram of a company

AI-generated content may be incorrect.


 

 

 

 

 

Attachment II

 

Organization Chart of Contract No. NL/2020/06

China Railway Group Limited (CREC)


 

 

A close-up of a diagram

AI-generated content may be incorrect.

 

 

 

 

 

 

Attachment III

 

Organization Chart of Contract No. NL/2023/10

CREC Joint Venture (CRECJV)

 


 

 

A diagram of a company

AI-generated content may be incorrect.

 

 

 

 

 

Attachment IV

 

Organization Chart of Entrustment Agreement No. ENT/TUE/001

Bouygues Dragages (1201) Joint Venture (BDJV)

 


 

 

 

A organization chart with text

AI-generated content may be incorrect.

 

 

 

 

Attachment V

 

Organization Chart of Environmental Team (ET) for TCW


 

 

 

A chart with text on it

AI-generated content may be incorrect.

 

 

Attachment VI

 

Organization Chart of Independent Environmental Checker (IEC) and the Supporting Team

 

 

 

A close-up of a document

AI-generated content may be incorrect.